The production of Lockheed Martin’s F-35 joint strike fighter (JSF) aircraft is expected to cost more and see a delay of up to three years before its delivery to the US Government.
The projections, based on a preliminary analysis of test and production data, reveal that software, engineering and flight difficulties related to JSF production are greater than expected.
Discover B2B Marketing That Performs
Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.
A F-35 technical baseline review was prepared by the Pentagon’s defence acquisition board for an in-depth examination of the $382bn JSF programme, according to Bloomberg.
New delays and higher prices are expected to cause difficulties in the development and combat testing of the F-35, which is already four years behind schedule.
The delay will lead to the $50bn development phase costing $5bn more, and the JSF being significantly more expensive to maintain than the warplanes it will replace.