The US Air Force has performed the first accelerated packaged maintenance plan (PMP) on a deployed F-22 Raptor aircraft.
The PMP, performed by airmen of the 27th Expeditionary Aircraft Maintenance Unit, is scheduled, long-term, heavy maintenance on a fighter aircraft performed after every 300 flight hours.
Discover B2B Marketing That Performs
Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.
It normally takes a month to complete, but deployed unit officials are tasked to accomplish an accelerated PMP in ten days.
During the PMP, a low observable team will select any panels the PMP inspection team may need to get into.
The inspection team will check their list to ensure everything is operational, and re-panel the aircraft and hand it back over to the low observable team for re-layering the jet.
An aircraft is grounded and will not be allowed to fly until it has gone through a proper inspection once it comes within 30 to 40 flight hours to its next scheduled PMP.